Economist Robyn Allan calls NEB process "rigged" and withdraws from Kinder Morgan Trans Mountain review

Economist and former ICBC president and CEO Robyn Allan withdrew from the National Energy Board’s (NEB) review of the Kinder Morgan Trans Mountain pipeline expansion project Tuesday, saying she can no longer “endorse a process that is not working.”

In a letter addressed to Sherri Young, secretary of the NEB, Allan said the “review is not conducted on a level playing field” and that because the panel is “not an impartial referee…the game is rigged.”

Allan said she began to seriously question the process when oral cross-examination was removed from the process.

“I had concerns with what that would do to the overall caliber of the process,” she said.

Allan said she wanted to “participate in good faith through the process of information requests” but now that it has been completed “it’s very clear it has been an exercise in futility.”

“I wanted to see the process through enough to unequivocally conclude that it’s broken,” she said. “Now I see it’s beyond repair.”

Allan said the limited scope of the board’s review of the process is an “unconscionable betrayal of Canadians.” 

“The board does not include the very serious issues the Canadian public expects the scope to include. And that’s not just the absence of greenhouse gasses in the review and the very serious implications of those for climate change — we don’t even have a classical economic scope of issues,” Allan said.

Allan said the review does not give full consideration to the impact the added Trans Mountain pipeline will have on the whole system, including the increase of tanker traffic in the Burrard Inlet.

Concerns are running high in the Vancouver area after the accidental release of bunker fuel from a cargo vessel in English Bay called the city’s oil spill response capabilities into question.

“You’ve see even just from the bunker C fuel spill in the Burrard Inlet that they were totally incompetent in their ability to deal with [a spill],” she said, adding that the board will only consider the incremental rise in tanker traffic in Vancouver’s waters resulting from the Trans Mountain expansion, but not the impact on tanker traffic as a whole.

“They’re not looking at the whole system,” she said. “This is a deception being perpetrated on the public.”

Allan also said the board relies too heavily on Kinder Morgan’s assessment of risk. Recently the City of Vancouver, City of Burnaby and Tsleil-Waututh Nation commissioned an oil spill assessment by modelling experts Genwest Systems that found two key faults with Kinder Morgan’s oil spill assessment.

Allan said she expects the board to support Kinder Morgan’s risk assessment over those submitted by third parties and downplay the significance of spill risks for the project as a whole.

More in News

Views from a refugee camp: Who gets into heaven?

I have just returned to Vancouver Island from Greek refugee camps where I met a Yazidi man named Jason who told me about his escape from ISIS in Iraq.   His story begins on a desert road where a...

Vancouver's bicycle sharing grows as 15 new stations installed

Mobi bicycle by Shaw Go in Vancouver. Photo by Christopher Porter from Flickr Creative Commons

International Women's Day Concert celebrates female musicians who turned tragedy into triumph

Every March 8, on International Women's Day, we hear about the achievements of brilliant, talented women around the world. But how often do we learn about the physical and mental disabilities or...
Speak up about this article on Facebook or Twitter. Do this by liking Vancouver Observer on Facebook or following us @Vanobserver on Twitter. We'd love to hear from you.